Project Information
- 📍 Location: Şanlıurfa, Karaköprü
- 📅 Completion: 2023
- 👥 Team: ~70–80 people
- ⏱ Duration: 4–5 months
- ⚙️ Service: Installation / EPC (large-scale site application)
- Partner: Şanlıurfa Water and Sewerage Administration General Directorate
Key Highlights
- Combination of large-scale fixed systems and tracking units.
- Operational success under challenging site conditions (earthquake/flood periods).
- Hybrid use of both fixed and tracking technologies.
Provided Benefits
- Long-term energy security for regional water and municipal infrastructure.
- Significant and permanent savings in electricity costs.
- Service continuity ensured through rapid commissioning.
Technical Details
- ~18 MWp installed capacity (fixed systems + ~550 kWp tracking sections).